Cleanroom costs consist of: supplying the technical installation, building the low dust rooms, energy costs and maintenance.

HIGHCARE cleanrooms supplies, manufactures and designs and provides on-demand maintenance.

Cleanroom costs

The cost consists of setting up the cleanrooms. Standard cleanroom costs per square meter (m2), such as a budget price, are unreliable and inappropriate to use. How so? The word cleanroom says nothing about content. Each project is unique in terms of layout and space requirements.

non-binding price indication, installation: €80,000 (25 m2), €250,000 (145 m2) and €1,000,000 (> 1,200 m2)

non-binding price indication, maintenance costs: € 8,500 – € 15,000

The prize

The price depends on variables such as: the number of rooms, room conditions, room size, cooling capacity, humidification technology, air filter cascade, utilities, et cetera. If you want a reliable price, we need to put together an estimate based on your data.

What is needed?

What is needed for a budget price? Are you in a hurry? Send us a simple sketch of your plans. Photos of the inside of the building in which you plan to place the rooms, clearly showing: height and width.

What affects the budget price: room height (m1), width (m1), number of rooms, total volume (m3), temperature, relative humidity.

Quality and specialty

What makes a HIGHCARE unique is its high classification. Air is extracted at plinth level in every room. Walls and ceilings are metal and simple to disassemble. The system is flat, sleek and modular. Each cleanroom is ISO certified upon completion by an independent firm. This international certificate is a recognition of quality.

For more than 25 years, this has been our standard

In a HIGHCARE, all materials are selected for their suitability. Production costs are low due to optimal standardization. The system is modular and quality is reliable; reproducible through industrial manufacturing. On site, products are assembled only.

A HIGHCARE is competitively priced

You buy from the makers. We only supply directly, no dealers or contractors. A HIGHCARE is portable and therefore also leasable. A HIGHCARE has a long economic life.

What does a clean room cost

What does a cleanroom cost is usually the first question and also the most difficult to answer quickly. A cleanroom is unique, different for each project and the indoor environment is highly dependent on use. A cleanroom is composed of – at least – four rooms and usually requires air conditioning in addition to air filtration. HIGHCARE supplies air-conditioned cleanrooms; ready to use.

What data is needed

A reliable budget price therefore requires more data. An outline of your plans is a first step. What will you use the cleanrooms for? Is there a known location? Do you have a drawing or photos of this location? Is a height of three meters sufficient? Do you have requirements for relative humidity, temperature? Where do you want windows? With these details, we can work out a first draft and determine a budget price.

Aeronautics

The air technology in a HIGHCARE is unique; three-dimensional. Every spot in the room is easily accessible for filtered air. The hollow clean room wall was specially developed for this purpose.
In a HIGHCARE, there is optimal synergy between walls, ceilings and all technology. Depending on the layout, we adapt the technology. Cleanroom prices depend on that. Will your project be large, small or there are more or fewer rooms, it has consequences for the technical design of the chiller and air handling unit and thus the price level.

HIGHCARE supplies a cheaper version, with PIR walls, called cold room elements, for an environment with fewer requirements. The PIR walls are not hollow. As a result, the spaces have less flushing and the walls are not fireproof.

Small and large projects, competitively priced

We believe that a budget price for a HIGHCARE should be complete, reliable and sharp. That is why we quote a stand-alone box-in-box system. So that it is immediately clear where the limit of delivery lies. This applies to both small and large projects. A HIGHCARE is basically separate from the exterior building and because cleanrooms are composed differently for each project, no standard price can be given. Cleanroom prices are an integral part of the 3D drawing program used by HIGHCARE. If the digital design is final, the price is fixed.

Detail questions, for a budget price

architectural

– what is the internal height of the cleanroom, the standard is 3 meters ( alternatives 3.5 ; 4, 6 or >6)
– the length and width of clean-room spaces
– The area of the overall clean room (Personnel, Clean-rooms, Goods In, Goods Out)

air treatment

– temperature and relative humidity in the clean rooms
– internal heat production; such as the number of operators, heating by the equipment used

technical installation

– utilities (technical supplies) compressed air, nitrogen, UPW, XCDA, 250V, 400V/16A, data, etc.
– desired ISO class or GMP, HCCP, IFS or BRC

A big help in putting together a price are a simple sketch of your plans, an architectural drawing of the outside box and photos of the inside of the outside box; the building/company hall.

Cleanroom price and size

The -total- volume of the cleanrooms is the basis for the cost. Together with the ISO classification, this determines the number of air changes to adequately condition the rooms. Will it be a cleanroom with four rooms; the minimum or are more rooms needed?

The best and fastest price estimate is created by sending HIGHCARE a principle sketch. To speed up the process, we would like to see your organization put together a handmade drawing and thus contribute to the design. Usually such a sketch is sufficient for a first price indication. Then a project engineer from HIGHCARE will make a 3D sketch.

In close consultation, we work out a detailed technical design. Your wishes and our experience eventually lead to a final design. This forms the basis for an indication of the contract price.

Synergy

In a HIGHCARE cleanroom, the synergy between walls, ceilings and air handling technology form the basis for high certification. We have been producing cleanrooms for more than twenty-five years. Compact sterile rooms, efficiently and flatly finished with lots of glass. Easy to keep clean and a safe and pleasant working environment.

Principle HVAC installation (conditioning)

– air treatment unit with filters: coarse, fine and or HEPA and or UV-C
– cooling and dehumidification, chiller
– humidification, steam humidification or adiabate
– heating, electric or with central heating

Cost per month, small clean room, value €100,000

A rough idea of the depreciation cost with this investment per month, without working out all the details, with depreciation over ten years.
€100,000 investment costs per month (€100,000/10)/12= €833.33.
This does not include insurance premium, interest, energy and maintenance costs.

Daylight in the workspaces

Cleanrooms should not be dreary workplaces; windows and light improve the working atmosphere. Lighting should be ample and equipment easily accessible so that it can be operated safely. Clean air should flow freely past all objects, so that the room rinses clean properly.(flush)

We want to eliminate mistakes in the design process by involving your company in the design. Technically, we pay attention to specific cleanroom requirements such as preventing air entrapment, making the cleanroom not flush clean properly -flush-, or easy to clean.(plumbing)

The cleanroom should not be too tight. In the design phase, the positions of equipment, windows, doors and inlet and outlet sluices are determined. Thanks to the “remountable” IFD construction technology, this is also simple to change during construction, or even afterwards.

A HIGHCARE cleanroom has the optimal possibility to flush the room clean due to its unique ventilation system. This guarantees a high classification.

<IFD construction technology>

Facilities

The range of utilities available is vast. The advantages of the hollow HIGHCARE wall system come into their own here. Utilities can be connected at more or less any location in the cleanroom.
Utilities such as:
– compressed air, XCDA
– drinking water, process water
– demineralized water, cold or hot
– UPW
– data connections
– electricity. Only 250 volts or also power current?

In the preliminary design, the entire plant is flexibly and standardly prefabricated with the desired features. Modifications and expansions are easily realized. The maximum available capacity is determined by the building utility connections. What is available in the building?

<NUTS COMPANIES>

The quality of building materials

The quality of construction materials is important for the economic life of the cleanroom and the safety of process operators. A HIGHCARE cleanroom is made of steel and glass panels. A flat and tight inert material that is very easy to clean, conducts electricity and is magnetic. In addition, dust and other dirt adhere poorly to steel, so all light dust particles are extracted during your production process. The elements connecting the various parts are also solid and safe. The cleanroom can be disassembled and moved.

Technology

The quality of the technical installation, such as the air handling unit and lighting, should be operationally reliable and economical in energy consumption. For these reasons, a HIGHCARE cleanroom is equipped with state-of-the-art technical components from internationally recognized manufacturers. The LED lighting has a service life of more than 50,000 hours.

Cleanroom prices

The construction method is pricing for this modular system and can be assembled quickly, cleanly and efficiently in your facility. A HIGHCARE cleanroom is built according to the revolutionary IFD philosophy. This stands for industrial, flexible and remountable building elements. With this technique, the entire cleanroom is literally built digitally before it is delivered in the form of a building kit.
The cleanroom prices are an integral part of the drawing program used by HIGHCARE. Once the digital design is finalized, the price is fixed.

At the construction site, HIGHCARE does not saw, sand, chip or paint. A clean, low dust construction method. This results in minimal inconvenience and a very fast construction time.

Certification

Cleanroom certification is the final stage of the construction process for HIGHCARE. We deliver upon completion the ISO classification agreed with you. An internationally recognized cleanroom certificate.
There are several relevant standards, such as GMP, HCCP, IFS or BRC.

HIGHCARE has experience with all common certifications.

<QUESTIONS ABOUT FINANCING OR LEASE? feel free to contact us >

The following information is required for an application:
– NAW, name and business address
– Chamber of Commerce number (an official excerpt is not required)
– Latest financial statements

Why can a HIGHCARE be leased?

HIGHCARE cleanrooms are demountable and relocatable. A HIGHCARE is not nailed to the foundation. In recent years, cleanrooms from HIGHCARE have moved and changed hands.